1) The organ being erected for testing in the factory
![]() |
(96-10-28)
[jpeg 79k] |
![]() |
Containers arrived (97-01-23) |
![]() |
Unloading (97-01-23) |
![]() |
Hundreds of crates and boxes with various organ parts ... about 20 tons in all.
(97-01-23) |
![]() |
Stage area and the organ :
... Scaffolding being prepared for the organ. (97-01-23) |
![]() |
Stage area and the organ
(97-02-18) |
![]() |
Hoisting the biggest Open Wood pipe |
![]() |
Stage area and the organ
(97-03-28) |
|
|
![]() |
Hoisting down the L.P. Blower.
(97-02-19) |
![]() |
The L.P. Blower, Reservoir and wind ducts installed.
(97-03-06) |